M/s Awadhesh Singh Gautam v. State of Chhattisgarh & Ors. — 2026 INSC 1072 (30 September 2026)

What the case was about

The Chhattisgarh Rural Road Development Agency withheld more than ₹84 lakh that a contractor had raised as running bills for three ongoing rural road projects (para 10). The State claimed the amount was needed to recover excess payments allegedly made under two earlier, separate contracts. The contractor argued that no clause in the agreements permitted the government to seize money due under one set of contracts to settle a dispute over another, and that the recovery order was issued without any notice or hearing (paras 14, 23.1). The Supreme Court was asked to determine whether any contractual provision authorised such cross-contract recovery and whether the order violated the principles of natural justice (para 17).

The key facts

M/s Awadhesh Singh Gautam, a partnership firm, was awarded three packages under the Pradhan Mantri Gram Sadak Yojana (PMGSY) under work orders dated 1 September 2023 and 5 November 2024 (para 3). After raising running bills for the work done, the firm found the payments blocked (paras 4, 10).

Earlier, on 3 January 2023, the firm had been awarded two separate road construction contracts (para 5). A committee later found an excess payment of roughly ₹2.01 crore in those earlier works and recommended recovery (para 6). Acting on this, the Tehsildar issued a demand note under Section 146 of the Chhattisgarh Land Revenue Code, 1959 (para 7), but the High Court quashed it on 5 March 2025 because the contractor had not been given any hearing (para 8). In the interim, an FIR was registered and a chargesheet was filed (para 9).

Relying on inspection reports, the Executive Engineer passed a recovery order on 27 September 2025 blocking ₹84,17,003 from the running bills of the three subsequent works (para 10). The contractor’s representation elicited no response (para 11). The High Court dismissed the resulting writ petitions on 7 January 2026, holding that the relief sought involved disputed questions of fact that could not be examined in proceedings under Article 226 of the Constitution (para 12).

The questions before the Court

The Court framed two issues for determination (para 17):

(i) Whether the recovery order dated 27 September 2025 was traceable to the contractual clauses relied upon by the respondents.

(ii) Whether, even if traceable, the order satisfied the conditions prescribed by such a clause and whether it was passed in violation of the principles of natural justice.

What the Court decided and why

The Supreme Court allowed the appeals, quashed the recovery order, and directed the State to release ₹84,17,003 to the contractor together with interest at 6% per annum from 27 September 2025 until the date of actual payment (para 28). The Court also held that there shall be no order as to costs (para 30).

The Court examined each clause cited by the State. It held that Clause 44.1 of the General Conditions of Contract deals with liquidated damages for delay in completion and does not apply to recovery of alleged overpayment found during a technical audit (para 19.1). Clause 53.1(ii) is attracted only when a contract is terminated for a fundamental breach of defects-liability obligations; neither the earlier works nor the subsequent works had been terminated on that ground (para 20.1). Clause 7(iv) of the Integrity Pact permits recovery from other contract dues only after a prior determination that the bidder violated the pact, which the recovery order did not record (para 21.1). As for Clause 38 of the Conditions of Contract, the Court noted that its invocation requires a breach to be ascertained and the contractor to be apprised of it; since no finding of breach and no notice preceded the order, this clause too could not sustain the recovery (para 22.1).

The Court then focused on Clause 4.1 of the Special Conditions of Contract, which specifically governs recovery after a technical audit. It held that this clause permits recovery only from the security deposit or dues payable under the very contract that was audited—in this case, the earlier works (para 23.1). About ₹1.07 crore remained due to the contractor under those earlier works, yet the State chose to recover from three unrelated ongoing packages instead (para 23.1). The clause further mandates that the contractor be given an opportunity to explain his case before any recovery, and that no recovery be made without orders of the CEO, CGRRDA (para 23.1). It was common ground that no hearing was afforded and the recovery order, issued by the Executive Engineer alone, did not disclose the approval of the Chief Executive Officer (para 23.1). The clause also requires action to be initiated within twelve months of completion of the audited work, and no material was placed to establish that date (para 23.1). Accordingly, the Court concluded that none of the clauses relied upon by the respondents, whether read singly or cumulatively, authorised the deduction from the subsequent contracts or the manner in which it was effected (para 24).

On natural justice, the Court observed that an alleged overpayment, until established in accordance with law, remains a disputed and unadjudicated claim and not an ascertained debt that can be appropriated from amounts payable under a separate, subsisting contract (para 25). Because the recovery order was passed without notice, hearing, or any prior approval required by the contract, it was in flagrant violation of natural justice (para 25).

The Court also held that the High Court erred in dismissing the writ petitions on the ground that the dispute involved questions of fact unsuitable for Article 226 (para 26). The legality of the appropriation from the subsequent contracts turned entirely on the construction of the agreement and compliance with its terms, not on the resolution of the underlying factual dispute regarding the earlier works (para 27).

The judgment clarified that the respondents remain free to pursue appropriate lawful recovery in respect of the earlier works, and that its observations shall have no bearing on the pending criminal proceedings or on the correctness of the alleged overpayment (para 29).

Why it matters

The ruling reinforces that government agencies must operate strictly within the four corners of their contracts. Recovery must be expressly authorised by the specific clause invoked and must comply with every condition precedent, including notice, hearing, and sanction by the competent authority (paras 23.1, 24). The judgment also underscores that a disputed and unadjudicated claim cannot be treated as an automatic debt that may be set off against unrelated payments (para 25). For contractors engaged in public works, the decision affirms that procedural fairness and the plain text of the agreement provide a meaningful safeguard against unilateral appropriation. Finally, it clarifies that when the legality of a recovery turns on contract interpretation rather than factual adjudication, courts can—and should—intervene under Article 226 of the Constitution (para 27).

By Sanjiv Narang, Advocate on Record, Supreme Court

Sanjiv Narang is an Advocate on Record in the Supreme Court of India.

Leave a Reply

Your email address will not be published. Required fields are marked *